4 images (click to enlarge, drag left or right for additional pictures)
Wastewater Treatment Plant Construction Upgrades
Client
Lake George Village
Cost
$16 Million
Scope
  • In Service as of April 2022
  • New HW Building & Associated Equipment
  • New Admin & Lab Building
  • 5,000 cy SBR/Digester Structure
  • New Chemical & Blower Building